Most metallic epoxy floors take 3 to 5 days to install. You can walk on the finished floor after about 24 hours, and it reaches full cure after about 7 days. So from the first day on site, plan for the space to be out of normal use for roughly a week and a half.
That is the short answer. Below is what happens on each day, why it can’t be rushed, and how to plan around it.
Why it takes days, not hours
We pour the four-layer Hychem Onyx Metallic Floor System: primer, coloured epoxy base, metallic design coat and clear sealer. Each layer has to cure enough before the next one goes on, and the design coat has to cure before it is sealed. The waiting is part of the build. It is what lets four layers perform as one floor.
Cure times also depend on temperature and humidity. A cold Melbourne winter week is slower than a mild one in spring, and we plan for that when we book you in.
The days below are a typical sequence. Your quote confirms the plan for your floor.
Before day one
A few things happen before any equipment arrives:
- Site visit. We measure the floor, look at the slab and test it for moisture. The concrete needs to be sound and, if it is new, cured for at least 28 days.
- Samples and colours. We bring real samples so you can see colours in your own light and choose the style of movement you like.
- Written quote. You get a fixed, itemised quote with the timing for your job. If you want to understand what goes into it, read what drives the price of a metallic epoxy floor.
- Booking. We agree a start date that suits your build or your household.
Day 1: Grind, repair and test
Preparation decides how long the floor lasts, so it gets a proper day.
The slab is diamond-ground to a CSP 2 profile. That removes laitance (the weak, dusty surface layer), old coatings and contamination, and leaves a clean, textured surface the primer can grip. Cracks and chips are repaired, and the slab is checked again for moisture.
If the readings are high, a moisture-vapour barrier is applied before the primer. That is an extra layer with its own cure time, so it can add to the schedule. You will know about it in advance.
Grinding is the noisy part of the job. The rest is quiet.
Day 2: Primer and base coat
First comes the primer. It soaks into the ground concrete, locks it down and creates the bond for everything above. It also helps stop air rising out of the slab and leaving pinholes in the finish.
Then the base coat goes on: a 100% solids, solvent-free epoxy in your chosen base colour. It is the tough body of the floor and the backdrop the metallics sit on, so its colour shapes the final look.
Day 3: The metallic pour
This is the day the floor gets its character. The Onyx design coat is poured and worked by hand while it is wet. There is a working window of about 30 minutes to shape the effect before the resin begins to set. As it self-levels, the metallic pigments drift, pool and settle into a pattern that can’t be repeated.
For this stage the room has to stay closed up and undisturbed. Dust, leaves, insects and footprints all show in wet resin, so keep doors shut and pets and children well away.
Day 4: Clear sealer
Once the design coat has cured, the clear sealer goes on. It gives the floor its glass-like surface, deepens the metallic movement and protects against scratches, stains and chemicals. This is also where your choice of gloss, satin or matte comes in, along with anti-slip if you have asked for it.
Why some floors take 3 days and others 5
On a small, straightforward floor in mild weather, some stages can share a day. Others need longer:
- large areas, or several rooms
- slabs that need a lot of repair or old coatings removed
- floors that need a moisture barrier
- cold or damp weather, which slows curing
- staged work, for example a shop that has to keep trading
Your quote sets out the plan for your floor, so you are not guessing.
After the last coat: curing
| When | What you can do |
|---|---|
| First 24 hours | Stay off the floor completely |
| After about 24 hours | Light foot traffic |
| Days 2 to 7 | Keep it light: no vehicles, no heavy furniture, nothing dragged or rolled |
| After about 7 days | Full cure. Park, furnish and use the floor as normal |
We confirm these timings for your job before we leave, because temperature can move them.
How to plan around it
Empty the space fully. Everything has to come out, including shelving and anything stored against the walls. Sort this before day one so no time is lost.
Plan your access. Nobody can cross the floor between coats. If the room is a hallway or the only path to the laundry, work out the detour first. In a garage with an internal door, plan to use another entry for the week.
Park elsewhere. Cars stay off a garage floor until full cure, so allow for about a week and a half on the street or driveway.
Sequence other trades. In a renovation or new build, the floor should go down after dusty work is finished. Talk to us or your builder about where it fits in the programme.
Keep it ventilated, but closed to debris. We will tell you what to open and when.
The short version
- Install, 3 to 5 days: grind and test, prime and base, metallic pour, seal.
- About 24 hours after the last coat: light foot traffic.
- About 7 days after the last coat: full cure and normal use.
If you have a deadline, such as a move-in date, a handover or an event, tell us when you request your quote. We will work back from it and tell you honestly whether it is achievable. To see the colours this process can produce, have a look at the metallic colour range.
- Installation
- Timeline
- Curing
- Preparation